Mounting procedure

Size 3300 mm - 5000 mm

S - Rotors (segmented rotors)
B - Casing (divided casing)

Mounting procedure11

Final assembly at the application site

Delivery of a rotorsystem to the construction site is in three parts:

  1. Casing bottom part with premounted rotor half and pre-mounted motor block
  2. Casing top part
  3. Segments still to be mounted

Detailed assembly instructions are included with the shipment papers.

Mounting procedure12

The casing top part is mounted on the lower casing according to the respective markings.

Mounting procedure13

To complete the mounting of the rotorsystem, the mounting corner M is screwed out.

Mounting procedure14

The segments are mounted one after the other according to the labelling. After that the mounting corner is reinserted.

After the V-belt has been mounted and the speed regulation device has been connected, the seals are adjusted. The rotorsystem is ready for operation.

Mounting procedure15

Important Note:

Segmented rotary heat exchangers can be ordered and delivered with pre-assembled rotor halves or without pre-assembled rotor halves.

Pre-assembled rotors shorten and simplify assembly at the end-use site.

An order with a pre-assembled rotor half should, however, only take place if it can be ensured that the pre-assembled rotor can be carefully transported to the end-use location. Shocks and impacts must be avoided, the component must not be tilted and should always be supported in the middle!

If the transport situation is unclear or problematic, the rotary heat exchanger must be ordered without a pre-assembled rotor half.

Please do not hesitate to contact us  in order to clarify the best possible solution for your application.